Posted at 11:18h
in
News,
Project Milestone
As the season of spring officially begins, site crews continue to take advantage of the good weather by making great headway at Swope Middle School.
“It is exciting to see the swift progress happening at the school, and we only have greater milestones in store as we embrace spring,” said Casey Gunther, Operations Manager for United Construction. “Our site crews are continuing with framing, retrofitting, HVAC installation, and many other finishes within the new classroom building, which is getting closer and closer to completion.”
During the Washoe County School District spring break, crews worked in both the new two-story classroom building and the existing school at the same time. In the new building, the team continued with rough-in mechanical, electrical, and plumbing. They are substantially complete with the metal stud framing on the first floor, and the next focus will be the soffits and ceilings. On the second floor, the team insulated the exterior walls and began metal stud framing there as well.
Within the existing school, site crews are finishing the retrofit of the HVAC system. They cut a large hole in the gable at the front of the building to install new equipment in the attic. Additionally, they are insulating specific areas of the ceiling to increase the R-value, which is a figure that measures how well insulation resists conductive heat flow.
In the north courtyard, the team has installed the new sewer line that connects the new two-story classroom building to an existing sewer line. On the northwest side, crews also began the installation of piping for the new chiller.
United Construction will continue to update neighbors with current construction information.
Photos by Ryland Sweigard