Holiday Season Construction at Swope Middle School

Holiday Season Construction at Swope Middle School

It’s the holiday season, and we would like to take this opportunity recognize all of the hard work our crews and partners are doing at Swope Middle School.

“As we pass Thanksgiving and continue into the December holidays, we are thankful for our employees as well as our subcontractors and Washoe County School District partners for all they have done for the students and staff,” said Casey Gunther, Operations Manager for United Construction. “All of the incredible milestones we have hit thus far are a testament to the talent and dedication of the entire team.”

The two-story classroom building will go vertical this month with masonry and structural steel. This means that the shell of the building will start to become visible by the Swope community. When finished, the building will house a new resource center, math and science classrooms, a technology lab, a new teachers’ lounge and workspace, social science and language classrooms, a group room for various activities, a new library and a hub space.

In regards to the existing classrooms, mechanical, plumbing and electrical upgrades are under way. This work will continue from now through the summer of 2022.

Early morning concrete slab pours plan to be wrapped up this week. Site crews commenced pours in the morning to reduce the amount of disruptions for staff and students during school hours, as well as prevent traffic jams at peak driving times and preserve the quality of the project.

The Ambassador Program is gearing up to start soon. As a part of the program, students can expect visits from industry professionals who will speak to them about several aspects of the construction industry, including contracting, architecture, design, engineering and more.