Project Milestone

Congratulations to the team for being granted a Temporary Certificate of Occupancy (TCO) for our Swope Middle School project! To celebrate this achievement our entire site crew including subcontractors, as well as Swope Middle School teachers, enjoyed a delicious lunch from Butcher’s Kitchen Char-B-Que. Two lucky crew members on our subcontracting team scored some YETI swag in a raffle as a special thanks for all of their hard work on this project.

Students will be welcomed back on Monday for their first day of school! The 3-phase project included a new gym and basketball courts, a new two-story classroom building, a new kitchen, and renovations to the older section of the building including an updated HVAC system. A new multipurpose room, administrative offices, nurses clinic, and courtyard are currently under construction and will be turned over to WCSD in phases by the end of this year.

The month of May marked an especially productive timeframe for the construction team at Swope Middle School. Site crews have reached completion or near completion on several aspects of both the interior and exterior of the new two-story classroom building and the existing classroom building.

“We are proud of the immense progress our team has made thus far at Swope,” said Casey Gunther, Operations Manager for United Construction. “This work is a testament to the dedication of our subcontractors, partners, and Washoe County School District.”

The roof atop the new classroom building is finished, and the building is dried in as well. The mechanical, electrical, and plumbing rough-ins are also substantially complete. Thanks to the quick work of our site crews, almost all walls and soffits are completely covered with drywall. Our team is now in the process of taping and texturing the interior walls, which will be followed by paint. On the exterior of the building, the areas in the north courtyard have been excavated for the six above-ground planters that are planned to be built. After the footings for the planters are poured, the forms will be stripped, and the concrete masonry units (CMUs) will be installed.

On the northwest corner of the new gym, the pad for the new chiller unit has been prepped for the concrete slab to be formed and poured. Crews have been working on the HVAC system in the attics of the existing classroom building after school every day, installing new duct work and mechanical equipment.

Concurrent with the physical work on site, United Construction has been meeting with their key subcontractors to plan the sequencing of all work planned to be performed during summer break.

Photos by Ryland Sweigard

Aristocrat Gaming, a global gaming content and technology company, recently held a groundbreaking ceremony at our planned logistics park in Henderson, Nevada. The company will be a tenant in one of the buildings, where they will manufacture slot machines and other gaming equipment.

Southern Nevada dignitaries, United Construction and their subcontractors, and hundreds of Aristocrat employees attended the event, excited to mark the beginning of the construction progress for their brand new building.

KLAS Channel 8 in Las Vegas covered the groundbreaking. The video clip that aired on TV can be found here.

We thank our Superintendent Kerry Brock for the logistical and on-site help and our Senior Project Manager Dane Horton for the planning support behind-the-scenes!

Students and staff at Swope Middle School are anticipating the completion of their brand new classroom building, as the site crews make notable progress witnessed by the Swope community.

“We are approaching new milestones that will help prepare us to welcome students and staff into their revamped learning space upon project completion,” said Casey Gunther, Operations Manager for United Construction. “We appreciate everyone’s patience and enthusiasm as we shape up the expansions and renovations at the school.”

In the new two-story classroom area, the on-site construction team is in the process of installing the new roof. Upon roof completion, the building will be dried-in. Crews have “one-sided” the drywall in several sections on the first floor and will continue this work on the second floor after roofing work is complete. After the building is dried-in, the team will be able to use a crane to install the new mechanical equipment onto the roof towards the end of this month. Additionally, all the metal stud framing is complete. Crews will continue to work on the rough-in of the mechanical, electrical, and plumbing systems, and this process should be complete in the coming weeks.

Concurrent to the performance of the physical work on-site, United Construction is holding pre-installation meetings with key subcontractors to plan work on the existing classroom building. Their goal is to commence work that can be done before Washoe County School District releases for the summer, as well as the work that will need to be performed during summer break.

United Construction will continue to update neighbors with current construction information.

Photos by Ryland Sweigard

Our Park at McCarran project and field team welcomed the NAIOP Northern Nevada Developing Leaders onsite yesterday for a tour of Buildings 1-3. We had a great time showing these young construction and development professionals the immense progress of the park, both inside and outside. They were a delight to have! Thank you, Developing Leaders, for taking the time out of your day to experience the Park at McCarran construction site!

As the season of spring officially begins, site crews continue to take advantage of the good weather by making great headway at Swope Middle School.

“It is exciting to see the swift progress happening at the school, and we only have greater milestones in store as we embrace spring,” said Casey Gunther, Operations Manager for United Construction. “Our site crews are continuing with framing, retrofitting, HVAC installation, and many other finishes within the new classroom building, which is getting closer and closer to completion.”

During the Washoe County School District spring break, crews worked in both the new two-story classroom building and the existing school at the same time. In the new building, the team continued with rough-in mechanical, electrical, and plumbing. They are substantially complete with the metal stud framing on the first floor, and the next focus will be the soffits and ceilings. On the second floor, the team insulated the exterior walls and began metal stud framing there as well.

Within the existing school, site crews are finishing the retrofit of the HVAC system. They cut a large hole in the gable at the front of the building to install new equipment in the attic. Additionally, they are insulating specific areas of the ceiling to increase the R-value, which is a figure that measures how well insulation resists conductive heat flow.

In the north courtyard, the team has installed the new sewer line that connects the new two-story classroom building to an existing sewer line. On the northwest side, crews also began the installation of piping for the new chiller.

United Construction will continue to update neighbors with current construction information.

Photos by Ryland Sweigard

Crews are making great progress at the project site of our industrial 664,000-square-foot inventory facility in North Las Vegas. Superintendent Colton Brock is celebrating the fact that the pad subgrade is about 90% completed, and only 40,000 yards of export remain. Additionally, crushing for Type-II is currently taking place onsite.

Additionally, swift progress is afoot at our logistics project in Henderson. Our work on this project will initially consist of two logistics buildings (of a four-building project). Building 1 will be 330,000 square feet, and Building 2 will be 265,000 square feet. Under-slab utilities for those first two buildings have recently been completed, and according to Superintendent Kerry Brock, crews are beginning the tie-ins for the sanitary, storm, and water systems. Up next, the team will start digging footings.

Below, the photo to the left features March progress at our North Las Vegas site, and the photo to the right highlights our Henderson project, also in March.

 

 

If you’ve driven through the Mill Street and McCarran intersection in Reno recently, you may have noticed a new structure tilted up at Park at McCarran. Our site crews recently finished tilting one of the industrial buildings, marking the completion of a major milestone for the project. Superintendent Chuck Brown oversaw the progress onsite and ensured the tilt-up commenced safely and efficiently. Drone photography done by Ryland Sweigard (along with a corresponding video) showcases this successful process.

Site crews at Swope Middle School continue to quickly hit major construction milestones, especially in regards to the new two-story classroom building.

“We are thrilled to be about a quarter of the way through with the final phase of the expansions and renovations at Swope,” said Casey Gunther, Operations Manager for United Construction. “Our team has been using the dry weather this winter to their advantage and making great progress, so students and staff can start making more use of their new facilities.”

Site crews have completed the concrete masonry unit walls for the new two-story classroom building and scaffolding has been removed. Structural steel, including roof beams and columns, and second-floor concrete slabs are also complete, and exterior grid insulation and steel stud framing is currently underway. United Construction and crews are working after school hours on mechanical, plumbing and electrical upgrades within the current classroom building.

The new library will be housed within the new classroom building. While construction is underway, students are still utilizing the temporary library set up in the activity room of the new gym.

Inside the new kitchen, walls have been painted, and the epoxy floor is in. The facilities are close to completion and will soon be ready for use.

Please note that neighbors will continue to see increased truck traffic as site work continues throughout the school year. Be advised that safety and road controls will always be put in place whenever needed. United Construction will continue to update neighbors with current construction information.

Photos by Ryland Sweigard

Work on the grounds of the planned 664,000-square-foot inventory facility in North Las Vegas continues onwards into the new year, reaching new milestones and exciting moves. According to Superintendent Colton Brock, crews have 150,000 yards of export remaining out of their 430,000-yard operation, with under-slab utilities set to be installed at the end of February. Concrete is also on the horizon soon.

Towards the end of last year, crews also commenced rock blasting to quickly and cost-effectively remove rock from the site, which helped them immensely with an efficient mass grading process.

Colton happily reported, “It’s nice to have seen this progress during and after the lengthy grading portion of this project!”

Check out the most recent drone flyover of the site of the industrial project here, some awe-striking footage of the rock blasting here, and photos below!