Yard exports almost complete at site of planned North Las Vegas inventory facility

Yard exports almost complete at site of planned North Las Vegas inventory facility

Work on the grounds of the planned 664,000-square-foot inventory facility in North Las Vegas continues onwards into the new year, reaching new milestones and exciting moves. According to Superintendent Colton Brock, crews have 150,000 yards of export remaining out of their 430,000-yard operation, with under-slab utilities set to be installed at the end of February. Concrete is also on the horizon soon.

Towards the end of last year, crews also commenced rock blasting to quickly and cost-effectively remove rock from the site, which helped them immensely with an efficient mass grading process.

Colton happily reported, “It’s nice to have seen this progress during and after the lengthy grading portion of this project!”

Check out the most recent drone flyover of the site of the industrial project here, some awe-striking footage of the rock blasting here, and photos below!